A client contacted Winner Law Firm with a problem that the counterparty had been ignoring its obligations under the contract for three years, resulting in a debt. The private enterprise tried to resolve the situation without going to court, but the individual entrepreneur only partially paid for the services provided. And the client knew that the No. 1 company in economic litigation, which has positive reviews and high-profile cases, would help him quickly receive the full amount.
In the contract, the parties stipulated that the contractor has the right to use spare parts and materials to perform the work, the cost of which is included in the cost of the work performed and the ownership of which is transferred to the customer after the parties sign the acts of the work performed.
But the individual entrepreneur-customer apparently forgot about this clause of the contract and refused to pay the cost of the materials.
Moreover, he did not appear at the court hearing, did not send an authorized representative to previous court hearings, and did not inform the court of the reason for his absence, although he was duly notified of the date, time and place of the case. Court hearings were constantly postponed.
But finally, the lawyers of the Winner Law Firm convinced the court that the client was right and restored justice by returning his money.
Winner Law Firm is your victory.